Cudahy closes its right-of-way to work for four months of the year. If any part of your job touches the strip at the street, that single fact matters more than every price you are about to be quoted.

Request an estimate

We pour across the south suburbs and Cudahy is the one where the calendar, not the budget, most often decides what happens. Worth reading before you start collecting quotes, because the timing question has a hard edge here that it does not have next door.

The four months nothing happens at the road

Straight from the City, in its own words: "There is a moratorium on work in the City's Right-of-Way between December 1st and April 1st unless it is an emergency (i.e. sewer collapse)."

That is a third of the year during which your approach cannot be rebuilt, your public walk cannot be replaced, and nothing else in that strip gets touched unless something has actually failed.

Two consequences worth planning around.

Work backwards from the first of December, not forwards from today. A job that misses the cut-off does not move by a couple of weeks, it moves to April. Autumn is the point at which that stops being theoretical, and it is why quotes taken in September are worth more here than quotes taken in November.

The moratorium is about the right-of-way, not your garden. A patio, a garage slab, a path behind the property line: none of that is governed by it, weather permitting. So a Cudahy homeowner who wants both should expect the back-garden half to be far easier to schedule than the half at the street.

Replacing an apron is permitted work

The City names replacing your driveway apron or public sidewalk in its list of work needing the correct Public Works permit, alongside water and sewer laterals, putting a dumpster in the road, and development projects.

Worth saying plainly, because the usual assumption runs the other way: putting back what was already there is not treated as maintenance. If a bidder has not mentioned the permit, they have not accounted for the sequence either.

Questions about the permit process go to Public Works on 414-769-2212.

Who is allowed to work in the right-of-way

Cudahy attaches two things to right-of-way work beyond the permit itself: a Contractor's License and insurance requirements, with the application material going to the Engineering Department.

We are not going to put numbers on either of those here, because the conditions live in documents the City publishes and they should be read from the City rather than paraphrased by a contractor. What matters to you is simpler: ask a bidder whether they are licensed for right-of-way work in Cudahy, before they come out. Somebody who works here answers in a sentence.

Engineering, not Inspection

The department that owns this work is Engineering. The City lists driveway approaches with streets, sidewalks, pavement, storm sewer and private site development grading and drainage plans as Engineering responsibilities.

A small thing that saves a wasted phone call, and a slightly larger thing if your project changes drainage: grading and drainage plans sit with the same department, so a driveway that alters where water goes is a conversation with people who are already looking at your street.

What we lay in Cudahy

  • Concrete driveways, with the road end planned around the winter closure rather than into it.
  • Concrete patios, walks and sitting areas, which sit behind the property line and schedule far more freely.
  • Concrete repair, including apron replacement, which is permitted work here.
  • Garage and shed slabs, and steps.

How a Cudahy job runs

1. Four questions, and one date

Tell us what you want and whether it reaches the road. If it does, we start from the calendar rather than the drawing.

2. Licence, permit, then a slot

The Engineering paperwork goes in first. We give you a date the City can actually agree to, which in the autumn is the only kind worth having.

3. We pour it

Ground put right, forms set, poured, finished, jointed, and the street left as we found it.

Reading before you commit

Free on-site estimate in Cudahy

Four quick questions and a local concrete contractor gets in touch to arrange a free on-site estimate. If your job touches the right-of-way, we will tell you honestly which side of the winter closure it lands on.

Request an estimate

Sources

  1. City of Cudahy, Public Works Permits - the right-of-way moratorium between December 1st and April 1st with emergencies excepted, the permit requirement for replacing a driveway apron or public sidewalk, and the permit enquiry line. Read 2026-09-09.
  2. City of Cudahy, Right-of-Way Permits - contractor licence application, insurance requirements and contractor requirements, submitted to the Engineering Department. Read 2026-09-09.
  3. City of Cudahy, Engineering Department - responsibility for driveway approaches, streets, sidewalks, pavement and private site development grading and drainage plans. Read 2026-09-09.

Request an Estimate

Get your free, on-site estimate.

Tell us about your project and we'll call you back the same day to set up a free measure and price.

Get your free quote

Tell us about your project and we will call you back the same day. No obligation.

What are you looking to do?
Roughly how big?
When are you thinking?

Pricing it out is fine. We will not chase you.

What is your ZIP code?

So we can confirm you are in the service area.

Where should we send it?

Free, no-pressure estimate · Serving Milwaukee County, WI

By submitting, you agree to our Privacy Policy and Terms, and consent to be contacted by phone, text, or email about your project, including by automated means. Consent isn't a condition of purchase. Msg & data rates may apply.

Call us - get a free quote